All of us at Waterford United Church
are excited to be home in our new sanctuary
following the devastating fire in April 2008.
Our Church Members and those in our Church Neighbourhood
are extended a warm welcome to attend both the
morning service at 10:30am and the afternoon
Official Opening on Sunday September 19, 2010 at 2:00pm.
We are very pleased that
Mardi Tindal, Moderator of the United Church of Canada
will be present to participate in this happy occasion.
Ribbon Cutting ~ Special Music
September 13, 2010
August 24, 2010
Thank You Thank You Thank You
We want to take this opportunity to extend our sincere gratitude for all of the support - financial and emotional - that the Town of Waterford and the surrounding area has shown our congregation since the fire at our church in April 2008.
In this tumultuous time we were blessed to belong to a community who so visibly stood behind us and our future.
For all of this we Thank You.
Waterford United Church
2010
In this tumultuous time we were blessed to belong to a community who so visibly stood behind us and our future.
For all of this we Thank You.
Waterford United Church
2010
Official Opening September 19, 2010
The Official Opening of our new building will be held on Sunday, September 19, 2010. Mardi Tindal, Moderator of the United Church of Canada will be joining us.
June 28, 2010
Community Open House
A Peek Inside
"Sanctuary view from back of hall"

"Windows at Main Entrance on Church Street"


"Memorial Hallway" looks onto Church Street where a Memorial Garden will be planted.
Here is a peek at the (finished but unfurnished for the most part) product. We are pleased to be using the sanctuary and the large Sunday School Room. There are still lots of bumps to be ironed out - audio-visual systems, the furnishings, paint touch-ups here and there - but the overall feeling is that we are home.
"Windows at Main Entrance on Church Street"
"Memorial Hallway" looks onto Church Street where a Memorial Garden will be planted.
Here is a peek at the (finished but unfurnished for the most part) product. We are pleased to be using the sanctuary and the large Sunday School Room. There are still lots of bumps to be ironed out - audio-visual systems, the furnishings, paint touch-ups here and there - but the overall feeling is that we are home.
April 29, 2010
Week 41
No photo this week, just a written update of whats going on inside. The pews were being delivered and installed this week and the pipe organ is on its way from Montreal.
All of the flooring - hardwood and tiles - is complete as is the painting as well as the sound system.
Everyone is working very hard to be able to get into our new building soon!!
All of the flooring - hardwood and tiles - is complete as is the painting as well as the sound system.
Everyone is working very hard to be able to get into our new building soon!!
April 6, 2010
Week 38
Work is moving along very quickly now and huge changes are happening daily. Light fixtures are being installed in the sanctuary and the tile flooring is being laid in the foyer. The next major jobs will be the wood flooring installed in the sanctuary and the organ install.
March 28, 2010
February 24, 2010
Week 32
February 7, 2010
Week 30
January 29, 2010
January 16, 2010
Re-Post of Drawings

To re-fresh our memories and so to compare the actual building
to the plans, here are the drawings for comparison.
The following rooms have been re-purposed but will sizes remain as shown:
The Common Classroom on the south side of the sanctuary has been divided in half and the newly formed room on the west side will house The Archives.
The Secretary/Treasurer Office shown on the north side of the sanctuary has been moved to the current parlour.
The space left by moving these 2 rooms (and the removal of the joint wall) is accommodating a large parlour easily accessible off the vestibule/memorial area.
As well, the AVR room shown on the south side of the sanctuary will be a "Baby/Crying Room" with visual access to the sanctuary, the AVR will be housed in a room under the stairs at the north east corner of the sanctuary.
January 11, 2010
Week 27
As you can see there has been a lot of progress since the last post. The weather is now a factor in the work that can be done but the building has undergone signifigant improvements.
View from across Main Street at the front of the main sanctuary.
December 15, 2009
December 7, 2009
November 19, 2009
Week 19
Construction has re-started at WUC and we are looking forward to visible progress now as they work to install the structure needed to support the steeple and work on enclosing the building before winter weather. Many of the windows have been installed as they work towards enclosure.
October 17, 2009
September 17, 2009
September 5, 2009
August 21, 2009
Week 6 of Construction
August 1, 2009
A New Beginning
After a Ground Breaking Ceremony on June 28, 2009, construction began on the new building (as described in the drawings below) located at the corner or Main and Church Sts in Waterford.
Excavation began the week of July 13 and in these photos, taken at the end of July the footings are complete and the forms for the foundation are in place.
April 29, 2009